Construction of the tank N12 at LPH
Airport Bratislava
Complete execution of the construction.
Year of implementation: 2014
Investment costs: 2 750 000 €
-
Central oil trap modification
Airport Bratislava
Mechanical part installation.
Year of implementation: 2010
Investment costs: 651 000 €
-
Spent ADF processing – de-icing station
Airport Bratislava
Technical and economical study.
Year of implementation: 2010
Investment costs: 13 400 €
-
Central oil trap modification
Airport Bratislava
Design documentation for building permit and realisation.
Year of implementation: 2010
Investment costs: 77 500 €
-
Drainage system for the Storage tanks N12 and N13.
Airport Bratislava
Design documentation and erection
Year of implementation: 2009
Investment costs: 26 600 €
-
JET A1Storagege capacity expansion and unloading area modification
Airport Bratislava
1.stage of storage vessel erection and Oil separator installation.
Year of implementation: 2009
Investment costs 348 500 €
-
JET A1Storagege capacity expansion and unloading area modification
Airport Bratislava
Documentation Generel and Documentation for building permit installation of 2 storage tanks.
Year of implementation: 2009
Investment costs: 122 800 €
-
Recuperation unit of aviation fuel vapors
Airport Bratislava
Project documentation of mechanical part + delivery of the Flexible piping Brugg Rohrsystem and the dry quick-couplings TODO
Year of implementation: 2004
Investment costs: 26 600 €
-
Safety vale vent line to storage vessels
Airport Bratislava
Project documentation of mechanical part + delivery of the Flexible piping Brugg Rohrsystem
Year of implementation: 2001
Investment costs: 19 900 €