Reconstruction of loading lines for acids and lyes
Brenntag Pezinok
Project documentation + execution.
Year of implementation: 2012
Investment costs: 72 000 €
-
Mixture station for H2SO4
Brenntag Sl.Ľupča
Project documentation + execution.
Year of implementation: 2012
Investment costs: 194 000 €
-
Unloading, storage and distribution of H2SO4
Brenntag Sl.Ľupča
One stage project documentation + partial delivery of Process Control and Pumps
Year of implementation: 2009
Investment costs: 39 800 €
-
Storage system of liquid glucose – III. phase
Brenntag Slovakia, s.r.o.
Project for the construction permit and realization, complete delivery of machine, measurement and control part
Year of implementation: 2007
Investment costs: 36 500 €
-
Unloading of NaOH from the tank wagons, storage system and distribution
Brenntag Sl. Ľupča
Project for the construction permit and realization, delivery of pneumatic pumps Blagdon and parts for measurement and control.
Year of implementation: 2006
Investment costs: 49 800 €
-
Mobile device for filtration, tank pumping and trade dosing into the barrels.
Brenntag Slovakia
Suggestion, documentation and delivery of the complete device for filtration, pumping and dosing through the flammable fuids trade gauge
Year of implementation: 2005
Investment costs: 46 500 €
-
Storage system of liquid glucose – II. phase
Brenntag Slovakia
Project for the construction permit and realization, complete delivery of machine, measurement and control part
Year of implementation: 2005
Investment costs: 45 000 €
-
Storage system of liquid glucose – I. phase
Brenntag Slovakia
Project for the construction permit and realization + complete delivery of machine, measurement and control part
Year of implementation: 2005
Investment costs: 53 100 €
-
Caustic soda unloading station and weight dosing system into containers
Brenntag Slov. Ľupča
Project documentation, delivery and installation of pneumatic pumps Blagdon.
Year of implementation: 2003
Investment costs: 26 600 €